GROWTH & INFRASTRUCTURE ...
Goal 2 – Protect and Manage Natural Resources
Objective M. ID
Measure
Lead
Target
Complete the design/permit
process to start renourishment
project by FY 2023 Q1
22/23
GI-2.1
2.1.1
Protect and renourish the dunes/beaches.
Engineering
GI-2.1
2.1.2
Revise the Land Development Code for enhanced landscape
buffers along identified roadways.
Growth Mgmt Revision of Land Development
Code by FY 2024 Q3
GI-2.1
2.1.3
Update, renew management plans for county managed natural
resources.
Land Mgmt
One per year
GI-2.2
2.2.1
Complete RFP process and establish a timeline.
Tourism
Annual updates
GI-2.3
2.3.1
Develop beach access and parking plan for county shoreline.
Engineering
Plan completed by FY 2023 Q2
GI-2.3
2.3.2
Consider use of public transport to meet access requirements.
Engineering
Reviewed annually
GI-2.4
2.4.1
Complete Stormwater Master Plan.
Engineering
Plan completed by FY 2023 Q1
GI-2.4
2.4.2
Develop flood recovery and resilience plan.
Engineering
Plan completed by FY 2023 Q3
GI-2.5
2.5.1
Examine feasibility of density exchanges and transfer of
development rights for preservation.
Growth Mgmt Report prepared by FY 2025
Q3
GI-2.5
2.5.2
Examine acquisitions of tax parcels or other lands.
Land Mgmt
Analysis report completed by
FY 2023 Q3
GI-2.5
2.5.3
Report status of new acquisitions annually.
Land Mgmt
Report on status annually Q4
GI-2.5
2.5.4
Examine purchase of paper subdivisions.
Land Mgmt
Analysis report completed by
FY 2023 Q3
23/24