Job Book 9th Edition - Book - Page 74
ONLINE VERSION
62
Stage 0 > Strategic Definition: Supplementary Material: 0/SM5
Figure 0/2:
Specimen project resource planning sheet
Job no:
Job title:
Project resource planning sheet
Budget cost
Commencement
Completion
Estimated number of site visits
Stage
0
1
2
3
4
5
6
7
Start
Finish
Staff name/grade
32
32
64
64
20
80
20
20
33,200
C. Smith architect 60
32
64
160
320
400
360
80
40
87,360
W. Blaggs assistant
16
320
320
640
800
180
40
20
93,440
Expenses
2. List staff assigned to
job, grade, unit rate
and estimated hours
under Stages. Rates
should include for
overheads, profit and
reserves.
3. Enter estimated
expenses likely to
be incurred against
headings such as car
milage, travel fares,
subsistence, etc.
Hours Hours Hours Hours Hours Hours Hours Hours Total
Ivor Barch partner 100
Stage total
1. Estimate duration of
Stages with start and
finish entries.
£ per
hour
Total
40