330
Contractor Engagement
P.5.8.2
Monitor progress on party wall awards.
CA
P.5.8.3
Check all necessary statutory and other consents have been
obtained and that party wall awards are in place.
CA
If any permissions, consents or awards are still under negotiation during
the tendering process this could mean that alterations will be required to
the tender negotiations or that start on site will be delayed.
P.5.9
Cost planning
P.5.9.1
Provide information for the cost consultant to prepare a pretender cost estimate (or prepare a pre-tender cost estimate if
appointed to do so).
The pre-tender cost estimate is an essential check prior to inviting tenders.
At this point the estimate should be an accurate prediction of the tender
figures. The design and tender documents may need to be amended if
the estimate does not match the project brief.
P.5.9.2
Review with the client the implications of the pre-tender
estimate prepared by the cost consultant.
CA
P.5.9.3
Discuss possible options with the client. Explain implications for
timetable and consultants’ fees if amendments are required to
change (or comply with) the brief.
CA
P.5.9.4
Report to the client on cost matters at agreed intervals.
CA
If procurement is through design and build:
•for an employer client: provide revised information if relevant for
corrected cost estimates
•for a contractor client: provide revised information if relevant to the
contractor’s estimators.