6.5.4.9
Discuss with the client whether authorised photographers would
be allowed access after final completion, for Feedback purposes.
6.5.4.10 Discuss with the client whether it would be permissible for the
architect to carry out a survey of the building in use some time
after completion.
6.5.4.11 Check with your PI insurers that you have cover for Feedback
activities.
6.5.5
Project team
6.5.5.1
Involve the project team as required.
6.5.6
General matters
DLP activities
6.5.6.1
Administer the terms of the Building Contract.
6.5.6.2 Collate all documents issued to the contractor, and store them.
Preparation of ‘As-constructed’ Information and maintenance manuals
is included under Stage 5.
CA
CA
6/SM1
6.5.6.3 Conduct in-house appraisal of office performance on project.
6/SM2
6.5.6.4 Consider holding a debriefing exercise with the client and other
consultants.
6/SM3
6.5.6.5 Check if the building log book for the building operator –
required by Part L of the Building Regulations – has been
issued. The building log book should be in accordance with the
requirements of CIBSE TM31 (refer to www.cibse.org).