Stage 6 > Handover and Close Out
6.5.3.9 If a BREEAM assessment has been commissioned you may need
to provide information to the BREEAM assessor in order for the
post-occupancy stage of the assessment to be completed.
A full BREEAM assessment is undertaken in four to five stages (depending
on when the assessor is appointed), comprising: registration, preassessment, initial guidance/design stage assessment, construction and
post-construction review/final certification. A BREEAM certificate will not
be issued until after the post-construction stage of the assessment has
been completed.
For further guidance refer to www.bream.org.
POE activities
6.5.3.10 Check to see if the client wishes to undertake a BREEAM In-Use
assessment of the building in operation and agree the scope of
the service and the fee.
BREEAM In-Use is a scheme to help building managers reduce the
running costs and improve the environmental performance of buildings.
6.5.3.11 Check if the client wants to instruct a POE exercise and, if so,
agree the scope of service and the fee.
6.5.3.12 Advise the client of the need to employ other consultants and
the contractor.
6.5.4
Client
DLP activities
6.5.4.1
Remind the client that responsibility for insurance reverts to
them.