Job Book 9th Edition - Book - Page 295
ONLINE VERSION
Stage 6 > Handover and Close Out
However, this is a sensitive area and confrontation should
be avoided at all costs. A full Feedback study will not be a
productive exercise in all cases and great care needs to be
taken when deciding whether or not it will be worthwhile for
a particular project. The architect’s professional indemnity (PI)
insurers should be informed before such a study is undertaken
for the client.
6.2
6.2.1
6.3
6.3.1
6.4
Procurement
Conclude administration of the Building Contract. Refer to 6.5.6,
‘DLP activities’.
CA
Programme
There will be a prescribed programme for DLP activities after Practical
Completion, usually for 6 or 12 months. A programme for activities for
Soft Landings and POE will need to be agreed with the client during an
earlier stage, ideally in Stage 1.
(Town) Planning
There are no (Town) Planning activities during this stage, but the 6/SM2
planning process should be reviewed along with other matters in 6/SM3
the post-project reviews.
283
6