Job Book 9th Edition - Book - Page 287
ONLINE VERSION
Stage 5 > Construction: Figures
Figure 5/7
Specimen record form of defective work
Job no:
Job title:
Record of defective work
Date
1.8.13
Item
Contractor
notified
(date)
Value if
deducted
(£)
Cleared
(date)
Priming to some steelwork
2.8.13
2.9.13
16.9.13
12.10.13
unsatisfactory
16.9.13
Nosing to boiler house steps not
satisfactory, shuttering poor
1. Describe the work
in sequence of work
element/location;
condition as rejected;
rectification required.
2. Check and update
this record regularly
with clerk of works
and design team.
3. Notify cost consultant
of any values
deducted against
valuations made
and when items are
cleared.
4. Check against and
coordinate with
your site inspection
reports.
275