Job Book 9th Edition - Book - Page 286
ONLINE VERSION
274
Stage 5 > Construction: Figures
Figure 5/6
Specimen record form of site delays observed
Job no:
Job title:
Record of site delays observed
Date
Delay
Item
Reason
6.1.13
1 week
Site clearance Plant hire equipment late
C of W
17.1.13
1 week
Weather
Heavy snow
C of W
23.2.13
3 days
Foundations
Excavations waterlogged
C of W
10.4.13
2 days
Steelworks
Erectors arrived
Problem with crane jib
HRJ
Left site
1. Record observations
in sequence of work
element/location,
conditions or
situation and note the
source of information
where relevant.
2. Liaise closely with
clerk of works and
consultants.
3. Check against and
coordinate with
your site inspection
reports.
Observed by