Stage 5 > Construction: Supplementary Material: 5/SM11
Handover of building
The client accepts the building and site from the contractor, and the contractor
hands over the keys.
• Ensure that meters have been read and fuel stocks noted.
Maintenance manuals, servicing contracts, etc.:
• Confirm with the CDM coordinator the contents of the Health and Safety File
and the arrangements for delivering it to the client.
• Hand over any further building maintenance information as relevant,
including:
–– directory
–– servicing contracts
–– maintenance of plant
–– maintenance of building
–– attention to landscape and planting
–– routine replacement schedules
–– ‘As-constructed’ Information.