Job Book 9th Edition - Book - Page 254
ONLINE VERSION
242
Stage 5 > Construction
5.5.9.6
Deal with applications for reimbursement of direct loss and/or
expense fairly and promptly.
CA
5.5.9.7
Report to the client on cost matters at agreed intervals.
CA
5.6
Sustainability Checkpoints
Sustainability Checkpoint 5
With the design work complete the majority of activities at this stage are
in relation to ensuring that the commissioning and handover activities
agreed during Stage 1 are properly implemented.
Sustainability aims
To ensure that the Sustainability Strategy underpinning the
design is carried through into construction and to manage the
handover in a way that will ensure that the client can operate the
building as intended on occupation.
Checkpoints
• Has the design stage sustainability assessment been certified?
• Have sustainability procedures been developed with the
contractor and included in the Construction Strategy?
• Has the detailed commissioning and Handover Strategy
programme been reviewed?
• Confirm that the contractor’s interim testing and monitoring of
construction has been reviewed and observed, particularly in
relation to airtightness and continuity of insulation.
• Is the non-technical user guide complete and the aftercare
service set up?
• Has the ‘As-constructed’ Information been issued for postconstruction sustainability certification?