Stage 5 > Construction
5.5.6.10 Set up procedures to issue fee accounts regularly.
5.5.6.11 Confirm dates for commencement and completion.
CA
5.5.6.12 Clarify any queries from the contractor.
CA
5.5.6.13 Establish and inspect the contractor’s programmes and confirm
information schedules.
CA
5.5.6.14 Call for all the contractor’s insurance policies. Pass on to the
employer for checking by their brokers or insurance advisers.
5/SM4
CA
Check original documents carefully for cover and renewal dates. Do not
accept assurances.
5.5.6.15 Check bonds and warranties required from the contractor.
CA
These should be obtained before the Building Contract is signed – it may
be impossible to obtain them later.
5.5.6.16 Check that the CDM coordinator has expressed satisfaction with
the contractor’s construction phase Health and Safety Plan, and
that this is confirmed in writing.
CA
5.5.6.17 Carefully inspect the contractor’s preliminary programme,
particularly if it indicates dates by which critical information is
required. Comment as appropriate, but do not approve it.
CA
5.5.6.18 Check that the contractor has prepared a Health and Safety Plan
which is acceptable to the CDM coordinator.
CA
Under no circumstances can work start on site without a Health and
Safety Plan in place which conforms with the principles of the CDM
Regulations.
5.5.6.19 Check quality management proposals and procedures with the
contractor.
CA
5.5.6.20 Check proposed site planning and accommodation with the
contractor.
CA