Stage 5 > Construction
5.3
5.3.1
5.4
5.4.1
5.5
Programme
If acting as contract administrator, check that the contractor is
CA
working according to the Construction Programme and report to
the employer on this. The contractor will be expected to review
progress against the Construction Programme and annotate the
programme accordingly.
(Town) Planning
Monitor the contractor’s compliance with planning conditions.
Suggested Key Support Tasks
5.5.1
Information required
5.5.1.1
Check that all information necessary during Stage 5 is available,
which might include the following:
• form of Building Contract, with all necessary entries and
supplements, ready for completion by the parties
• contract documents, including drawings and bills of quantities/
specifications/schedules of work, incorporating any necessary
adjustments, ready for issue
• completed tender documents from the successful tenderer
• written records of any post-tender changes to the contracted
project
• administration forms published for use in contract
administration, suitable for the particular form of Building
Contract to be used
• contractor’s preliminary programme and required method
statements
CA