Stage 4 > Technical Design: Supplementary Material: 4/SM1
controlled. Risk of frustrated design work and perhaps abortive fabrication can
occur unless agreed procedures are adopted by the management contractor
and the design team.
3. Coordination and integration
The management contractor can expect to be closely involved in the appointment
of works contractors. This might be on the basis of developed detail drawings,
specifications and perhaps bills of quantities. Drawings prepared by the works
contractors will be mainly installation or shop drawings, and should be passed
to the architect by the management contractor for inspection with regard to
their integration and incorporation into the overall design.