Stage 4 > Technical Design
4.5.6.15 Enable access to the BIM model by the contractor(s).
4.5.6.16 Integrate subcontractor performance-specified work information
into the BIM model data.
4.5.6.17 Review construction sequencing (4D) with the contractor.
4.5.6.18 Share data for conclusion of design coordination and detailed
analysis with subcontractors.
4.5.6.19 Consider the requirements for the commissioning of engineering
services by subcontractors and the main contractor, and
provisions for testing for inclusion in tender documents.
4.5.7
Inspections/tests
4.5.7.1
Make such visits as necessary to supply sources (e.g. quarries,
brickyards, stoneyards) and manufacturing sources (e.g.
foundries, factories, workshops) before making final design
choices.
4.5.7.2
Arrange for further tests to be conducted on components, panels
and finishes, if appropriate and authorised by the client.
4.5.7.3
Decide on the provisions for testing to be included in the bills
of quantities/specifications/schedules of work, including the
contractor’s testing and commissioning of building services
before completion.
4.5.7.4
Determine provisions for the client to witness testing, if required,
and whether this is to be part of the contract period.
Establish the contractor’s obligations for attendance and
rectification if necessary.
4.5.7.5
Review quality management of potential suppliers and
subcontractors and their general compliance in health and safety
matters. Pass relevant information to the CDM coordinator.