Stage 4 > Technical Design
4.5.6.9 Complete the information with respect to prescriptive/
performance items in bills, etc.
Take care when including a provisional sum that the figure is adequate,
and that wherever possible it is for defined work.
4.5.6.10 Draft preliminaries (or project management sections)
together with work sections – specifications for materials and
workmanship (or systems, products and execution).
Use specification clauses which are clear and precise. It should be normal
practice to use the appropriate version of NBS Create. It is important that
the specification, in addition to bill of quantities, is incorporated so that it
forms part of the contract documentation.
4.5.6.11 Prepare and submit the Building Regulations submission and any
other third party submissions requiring consent.
Export data from the BIM model for analysis by local authority
building control.
4.5.6.12 Provide information as agreed to the cost consultant for
preparation of tender pricing documents (or prepare pricing
documents if appointed to do so).
4.5.6.13 If procurement is through design and build:
•for an employer client: check whether the client has confirmed in
writing acceptance of proposals and information supplied so far which
are to form part of the Employer’s Requirements
•for a contractor client: review any client’s comments on the detail
design or development and note any adjustments which may be
unavoidable owing to modifications introduced lately by component
manufacturers or specialist subcontractors.
Detail design amendments might also be necessary, for example,
because of substitutions forced by long delivery times.
Check what action is to be taken as a result.
4.5.6.14 Undertake a final review and sign off of the BIM model.