Stage 4 > Technical Design
4.5.4.11 Discuss with the client essential information for completing
contract documents (e.g. appendix) and which will need to be
referred to in preliminaries (or project management sections) of
specifications or schedules of work.
4.5.4.12 Check with the client any special or optional contract provisions.
4.5.4.13 Check with the client and advisers on insurance for works, etc.
4.5.4.14 Report regularly to the client on fees and expenses incurred, and
submit accounts at agreed intervals.
4.5.4.15 Check that the client settles all accounts promptly.
4.5.5
Project team
4.5.5.1
If appointed as information manager:
• assist members of the design team to develop the design
using the BIM model, ensuring that data-sharing protocols are
followed
• check and sign off the model at agreed stages
• issue or assist in the issue of design data at agreed times
throughout the development of the design
• assist in the development of data relative to the agreed levels
of detail
• assist in the integration of contractor’s, subcontractors’ and
suppliers’ data into the BIM model.
For further advice on working with BIM, refer to the RIBA
publication BIM Demystified (2012).
4.5.5.2 Establish or review project quality management procedures
together with relevant procedures of all design team members.