Job Book 9th Edition - Book - Page 193
ONLINE VERSION
Stage 4 > Technical Design
4.3
Programme
4.3.1
Check progress against the timetable for services regularly.
4.3.2
Confirm the stage timetable for services, and note its relationship
to the project timetable as agreed with the client.
4.4
(Town) Planning
4.4.1
Review with the design team implications of any conditions
attached to full planning permission.
4.4.2
Discuss with the planning officer the implications arising from
any planning permission conditions. If permission was refused,
discuss the reasons for the refusal and prepare, for the client,
recommendations as to the best course of action.
Revision of documents to comply with planning or other statutory
authority requirements does not form part of the Services under the RIBA
Standard Agreement 2010 (2012 revision) unless identified under Part 3
‘Other Services’.
4.4.3
4.5
In the event of a refusal of planning permission, amend the
scheme and re-submit the application as appropriate.
Suggested Key Support Tasks
4.5.1
Information required
4.5.1.1
Check that all information necessary during Stage 4 is available,
which might include the following:
• Developed Design as accepted by the client in written
confirmation, incorporating any agreed amendments
181
4