Stage 3 > Developed Design
3.2.5
Discuss with the client and the consultant team whether any
action will be needed on advance orders (noting the risk
involved in placing orders in advance of planning permission
being granted).
3.2.6
Identify works packages where applicable.
3.2.7
Identify any performance-specified work or contractor’s
designed portion items.
3.2.8
Discuss with the client any particular requirements for phased or
sectional completion.
3.3
3.3.1
3.4
Programme
Confirm the stage timetable for services, and note its relationship
to the project timetable as agreed with the client. The timetable
should show critical points by which information from the client
and design team members will be required.
(Town) Planning
Although it is set out as a ‘variable’ task in the RIBA Plan of Work 2013, it is
usual for the planning application to be submitted at this stage.
3.4.1
Prepare and submit application for approval of reserved matters
following an outline planning permission if appropriate.
3.4.2
Export data as appropriate from the BIM model to enable
preparation and submission of the application for full planning
permission, listed building consent and conservation area
consent as relevant and if instructed by the client. Ensure that all
applications are accompanied by relevant documents, including
payment by the client of the appropriate fee.