Stage 2 > Concept Design
2.5.5.7 Cooperate with the CDM coordinator and all other designers
in carrying out risk assessments and in drafting the preconstruction information.
2.5.5.8 Confirm the programme and pattern for design team meetings.
2.5.5.9 If appointed as information manager:
• organise a BIM pre-start meeting
• organise initial model sharing with the design team for
strategic analysis and options appraisal
• identify key model elements such as prefabricated
components and create concept level parametric objects for all
major elements
• enable design team access to BIM data
• agree extent of performance specified work
• assist members of the design team to develop the design
using the BIM model, ensuring that data sharing protocols are
followed
• check and sign off the model at agreed stages
• issue or assist in the issue of design data at agreed times
throughout the development of the design
• assist in the development of data relative to the agreed levels
of detail
• assist in the integration of contractor’s, subcontractors’ and
suppliers’ data into the BIM model
For further advice on working with BIM, refer to the RIBA
publication BIM Demystified (2012).
BIM data can be used for environmental performance and area analysis
at this stage.