Stage 1 > Preparation and Brief: Supplementary Material: 1/SM4
Additional duties for notifiable projects (Part 3 of the Regulations)
• Check a CDM coordinator and a principal contractor have been appointed
and HSE notified before starting work.
• Cooperate with principal contractor in planning and managing work,
including reasonable directions and site rules.
• Provide details to the principal contractor of any contractor whom he
engages in connection with carrying out the work.
• Provide any information needed for the Health and Safety File.
• Inform principal contractor of problems with the plan.
• Inform principal contractor of reportable accidents, diseases and dangerous
occurrences.
Everyone
• Check own competence.
• Cooperate with others and coordinate work so as to ensure the health and
safety of construction workers and others who may be affected by the work.
• Report obvious risks.
• Comply with requirements in Schedule 3 and Part 4 of the CDM Regulations
for any work under their control.
• Take account of and apply the general principles of prevention when carrying
out duties.