Job Book 9th Edition - Book - Page 118
ONLINE VERSION
106
Stage 1 > Preparation and Brief: Supplementary Material: 1/SM4
2
Management of the work
(a)
management structure and responsibilities
(b)health and safety goals for the project and arrangements for monitoring
and review of health and safety performance
(c)
arrangements for:
(i) regular liaison between parties on site
(ii) consultation with the workforce
(iii)the exchange of design information between the client, designers,
CDM coordinator and contractors on site
(iv) handling design changes during the project
(v) the selection and control of contractors
(vi) the exchange of health and safety information between contractors
(vii) site security
(viii)site induction
(ix) on-site training
(x) welfare facilities and first aid
(xi)the reporting and investigation of accidents and incidents, including
near misses
(xii)the production and approval of risk assessments and written systems
of work
(d)
site rules (including drug and alcohol policy)
(e)
fire and emergency procedures.
3
Arrangements for controlling significant site risks
(a)
Safety risks, including:
(i)delivery and removal of materials (including waste) and work
equipment taking account of any risks to the public, for example
during access to or egress from the site
(ii)dealing with services – water, electricity and gas, including overhead
powerlines and temporary electrical installations
(iii) accommodating adjacent land use
(iv)stability of structures while carrying out construction work, including
temporary structures and existing unstable structures
(v) preventing falls
(vi) work with or near fragile materials
(vii) control of lifting operations
(viii) the maintenance of plant and equipment
(ix)work on excavations and work where there are poor ground
conditions