34
Stage 7
In use
Task Bar
Tasks
Core Objectives
Undertake In Use services in accordance with Schedule of Services.
Procurement
There are no specific activities in the RIBA Plan of Work 2013.
Programme
There are no specific activities in the RIBA Plan of Work 2013.
(Town) Planning
There are no specific activities in the RIBA Plan of Work 2013.
Suggested Key
Support Tasks
Conclude activities listed in Handover Strategy including Post-occupancy
Evaluation, review of Project Performance, Project Outcomes and
Research and Development aspects.
Updating of Project Information, as required, in response to ongoing client
Feedback until the end of the building’s life.
Sustainability
Checkpoints
• Has observation of the building operation in use and assistance with
fine tuning and guidance for occupants been undertaken?
• Has the energy/carbon performance been declared?
Information
Exchanges
(at stage completion)
‘As-constructed’ Information updated in response to ongoing client
Feedback and maintenance or operational developments.
UK Government
Information
Exchanges
As required.
Variable task bar
Variable task bar
Variable task bar
www.ribaplanofwork.com