Guide to Using the RIBA Plan of Work 2013 - Other - Page 35
28
Stage 4
Technical
Design
Task Bar
Tasks
Core Objectives
Prepare Technical Design in accordance with Design Responsibility Matrix
and Project Strategies to include all architectural, structural and building
services information, specialist subcontractor design and specifications, in
accordance with Design Programme.
Procurement
The Procurement activities during this stage will depend on the procurement
route determined during Stage 1. The specific tasks carried out are listed under
the Procurement task bar in Figure 2.1.
Programme
The RIBA Plan of Work 2013 enables this stage to overlap with a number of
other stages depending on the selected procurement route.
(Town) Planning
The RIBA Plan of Work 2013 suggests that any conditions attached to
a planning consent are addressed during this stage, prior to work starting on
site during Stage 5.
Suggested Key
Support Tasks
Review and update Sustainability, Maintenance and Operational and
Handover Strategies and Risk Assessments.
Prepare and submit Building Regulations submission and any other third party
submissions requiring consent.
Review and update Project Execution Plan.
Review Construction Strategy, including sequencing, and update Health
and Safety Strategy.
A further review of the Project Strategies and documentation previously
generated is required during this stage.
Sustainability
Checkpoints
• Is the formal sustainability assessment substantially complete?
• Have details been audited for airtightness and continuity of insulation?
• Has the Building Regulations Part L submission been made and the design
stage carbon/energy declaration been updated and the future climate
impact assessment prepared?
• Has a non-technical user guide been drafted and have the format and
content of the Part L log book been agreed?
• Has all outstanding design stage sustainability assessment information
been submitted?
• Are building Handover Strategy and monitoring technologies specified?
• Have the implications of changes to the specification or design been
reviewed against agreed sustainability criteria?
• Has compliance of agreed sustainability criteria for contributions by
specialist subcontractors been demonstrated?
Information
Exchanges
(at stage completion)
Completed Technical Design of the project.
UK Government
Information
Exchanges
Not required.
Variable task bar
Variable task bar
Variable task bar
www.ribaplanofwork.com