Guide to Using the RIBA Plan of Work 2013 - Other - Page 33
26
Stage 3
Developed
Design
Task Bar
Tasks
Core Objectives
Prepare Developed Design, including coordinated and updated proposals
for structural design, building services systems, outline specifications,
Cost Information and Project Strategies in accordance with Design
Programme.
Procurement
The Procurement activities during this stage will depend on the procurement
route determined during Stage 1. The specific tasks carried out are listed under
the Procurement task bar in Figure 2.1.
Programme
The RIBA Plan of Work 2013 enables this stage to overlap with a number of
other stages depending on the selected procurement route.
(Town) Planning
It is recommended that planning applications are submitted at the end of
this stage.
Suggested Key
Support Tasks
Review and update Sustainability, Maintenance and Operational and
Handover Strategies and Risk Assessments.
Undertake third party consultations as required and conclude Research and
Development aspects.
Review and update Project Execution Plan, including Change Control
Procedures.
Review and update Construction and Health and Safety Strategies.
During this stage it is essential to review the Project Strategies previously
generated.
Sustainability
Checkpoints
• Has a full formal sustainability assessment been carried out?
• Have an interim Building Regulations Part L assessment and a design stage
carbon/energy declaration been undertaken?
• Has the design been reviewed to identify opportunities to reduce resource
use and waste and the results recorded in the Site Waste Management Plan?
Information
Exchanges
(at stage completion)
Developed Design, including the coordinated architectural, structural and
building services design and updated Cost Information.
UK Government
Information
Exchanges
Required.
Variable task bar
Variable task bar
Variable task bar