Guide to Using the RIBA Plan of Work 2013 - Other - Page 115
108
The client’s budget for the project, which may include
Project
Budget
the construction cost as well as the cost of certain
items required post completion and during the project’s
operational use.
The Project Execution Plan is produced in collaboration
Project
Execution
between the project lead and lead designer, with
Plan
contributions from other designers and members of the
project team. The Project Execution Plan sets out the
processes and protocols to be used to develop the design.
It is sometimes referred to as a project quality plan.
Project
Information Information, including models, documents, specifications,
schedules and spreadsheets, issued between parties
during each stage and in formal Information Exchanges at
the end of each stage.
The client’s key objectives as set out in the Initial Project
Project
Objectives
Brief. The document includes, where appropriate, the
employer’s Business Case, Sustainability Aspirations or
other aspects that may influence the preparation of the
brief and, in turn, the Concept Design stage. For example,
Feasibility Studies may be required in order to test the Initial
Project Brief against a given site, allowing certain highlevel briefing issues to be considered before design work
commences in earnest.
The desired outcomes for the project (for example, in the
Project
Outcomes
case of a hospital this might be a reduction in recovery
times). The outcomes may include operational aspects and
a mixture of subjective and objective criteria.
The performance of the project, determined using
Project
Feedback, including information about the performance
Performance
of the project team and the performance of the building
against the desired Project Outcomes.
The overall period for the briefing, design, construction and
Project
post-completion activities of a project.
Programme
A table that sets out the roles required on a project as well
Project
Roles
as defining the stages during which those roles are required
Table
and the parties responsible for carrying out the roles.