Rental costs are specified on the offer as well as Saturday, Sunday and public holidays, these are
damage waiver cost (if nothing is specified regard- considered for rental days. The rate for weekend
ing damage waiver, no damage waiver has been rental is determined based on an average month
added) and transport costs.
with 21 working days.
The rent is based on a maximum of 10 hours per
Invoicing and payment terms
When the monthly Rental period is over, the sup- working day. The supplier is entitled to the agreed
plier sends an invoice with a general payment rent, whether the supplies are in use or not. The
term of 8 days. For long term rentals, the supplier supplier has the right to cancel the rental without
is entitled to charge invoices for every 14 days or notice, including cancellation of rental agreeevery month after the supplier's wishes. If delay ments for later execution in the event of bankof payment, an interest rate is added, currently 2% ruptcy or suspension of rent, to release and pick
on the amount, per month. The charge of interest up the supplies for rent by the customer, if the
rate does not mean that the due date is altered. present conditions and obligations are not met by
The supplier has the right to charge advance pay- the customer or if payment is not Included in time.
ment if considered necessary. Any disagree- In this case, the supplier may, on its own initiative,
ments/disputes between the supplier and the cus- remove the rented supplies from the workplace,
tomer or any counterparty from the customer's and all expenses (including transport) shall be paid
side does not give the customer the right to post- by the customers. Customer can not expect to
rent the supplies beyond the agreed period. The
pone payment.
customer is during the rental period obliged to
The rental agreementĀ“s period and termination perform security checks on the supplies and daily
The rental period starts on the confirmed day of maintenance such as checking the battery water
on-rent and the supplies are disposal for the cus- levels, oil levels, charging of batteries, lubrication
etc. and keep the supplies clean and tidy. Only lubtomer. Bookings to the next day must be done
before 14.00, but for orders after this time to the ricants and oils dictated by the supplier must be
used.
next day, as well as same-day deliveries, will be
charged with an additional charge. When ordering after 14.00, for delivery the next day before
10.00 am extra fee of kr. 850,00,- will be added.
When ordering the same day as the desired delivery before 11.00, an extra fee of kr. 850,00,- will
be charged if transport is possible.
Off-rent of supplies can be done upon delivery of
the supplies at one of the suppliers depots, by direct inquiry on telephone +45 70 10 00 97 or
through My Riwal. Off-rent must be done before
16.30 - otherwise one extra day of rent will be
charged. When off-renting supplies you always get
a off-rent number as a receipt. The supplier is then
entitled to pick up and rent the supplies to others.
Obstacle access to the material, for whatever reason, rent is calculated until the supplies is easy accessible and ready for pick up. The rental period is
normally calculated as the number of weekdays
within the rental period; However, the insurance
will be debited by calendar day. If it is rented
Force majeure
In the occurrence of Force majeure, the supplier is
dismissed of obligation, as long as the Force
majeure situation occurs. Force majeure exists unless the supplier or the suppliers sub contractors
are prevented from fulfilling the agreements controlled by these general terms for rent of equipment and material as a consequence war, civil
war, riots, acts of terror, public restrictions, import
or export bans, natural disasters of all kinds and
work place conflicts, fire, power outs, computer
viruses or similar unless it can be proved that the
supplier could foresee the this when the Rental
agreement was made.
Legal court
Rental agreements with the supplier are controlled by Danish law and any legal disputes shall
be determined by the Danish court.