5.4 STATUTORY AND RECOMMENDED INSPECTIONS
5.4.1
The following steps relate specifically to inspection and testing requirements during the
‘implementation phase’. These are an additional range of controls that may be specified
in an inspection and test plan (ITP) and associated risk assessments for the activity
that involves constructing an item of temporary works.
Step
a. Inspecting prior to
inspection/dismantling
b. Inspecting during
installation/dismantling
c. Inspecting post-installation
d. Making good, packing,
storing and recording defects
Who is likely to be involved
Lead installer/supervisor/foreman and/or
TWC/TWS/supervisor/foreman and/or TWC/TWS or
another competent person
Note: inspections during construction should be
defined in the inspection and test plan (ITP) (if
required)
5.4.2
The PC’s TWC has specific duties related to inspection and testing. The SC’s TWC has
the same responsibility.
5.4.3
The TWS, where appointed, also has specific duties related to inspection and testing.
5.4.4
An inspection and test plan (ITP) is an inspection checklist of required inspections
required when building a structure. It lists task inspections and provides and easy
to follow plan to improve quality assurance. It's a plan that lists what tests and
inspections should be performed throughout each phase of a project.