4.2 THE TEMPORARY WORKS REGISTER
4.2.4
It may also be useful for the headings in your register to follow the stages or steps
set out in the companies process that may be broken down into steps within each stage.
Stage or Step
1. Identify
2. Plan
3. Design
4. Check
5. Implement the build
6. Implement the removal
Summary of actions required
Assess the activities that require
temporary works and prepare
temporary works register
Complete construction phase plan or
method of works, temporary works
implementation plan, develop the
temporary works register and issue a
design brief
Issue a design brief to the temporary
works designer
Issue the temporary works design
brief and design outputs to the
design checker and assess the
suitability of the proposed solution
Issue a design drawing or installation
guide suitable to construct from,
prepare method statement and issue
permit to bring into use
Prepare method statement and issue
permit to take out of use
figure 1 – CITB Form template - example of a temporary works register
figure 2 – TWf Form template - example of a temporary works register
Version 2 © mytemporaryworks 2023 | The control of temporary works – procedural guide