4.2 THE TEMPORARY WORKS REGISTER
4.2.1
The temporary works register should be populated during the pre-construction phase
or when scoping works.
4.2.2
The temporary works register enables actions to be tracked for each item of temporary
works on a project. It remains the responsibility of the PC’s TWC to keep it up to date
throughout the project.
4.2.3
BS 5975 provides a list of headings that should be included in the register: