Procedure
Applications requiring plan review must be “Round tabled” to determine which divisions will
need to review the plans. The round table procedure is the responsibility of the Building &
Safety Permit Technicians. Plans should be ready for round table review by 8:15 a.m. each
workday.
Prerequisites
1. Plans and all required documents are received.
2. Plan review fees must be paid.
Step 1 – Accept plans in AMANDA
1. In AMANDA, find and display the permit folder.
2. Click the {Process} tab.
3. Click the Application Intake process to display the attempt result slide-out as shown
below:
Page 4 of 6