iii. A narrative describing the systems and components to demonstrate compliance required in the Minimum
Life Safety Requirements section of this document.
3. Fire evacuation plan
Fire evacuation plans shall include the following:
a. Procedures for assisted rescue for persons unable to use the general means of egress unassisted.
b. Procedures for accounting for occupants after evacuation has been completed.
c.
Identification and assignment of personnel responsible for rescue or emergency medical aid.
d. The means of notifying occupants of a fire or emergency.
e.
The means of reporting fires and other emergencies to the fire department or designated emergency response
organization.
f.
Identification and assignment of personnel who can be contacted for further information or explanation of
duties under the plan.
4. If electrically-powered equipment will be used during the temporary occupancy that does not plug into an existing
receptacle, load calculations for the panelboard serving the space prepared by a licensed electrical engineer will be
required for review. The calculations must document that the wiring to the panelboard and the overcurrent device
rating ahead of the panelboard are not overloaded by the addition of the equipment.
If a generator will be used during the temporary occupancy, an electrical permit and inspection will be required
where the generator is rated 5KW or above. Refer to policy NEC 509 - Temporary Power and NEC 590.4 – Cable
installation for temporary special events for additional information. A fire department operational permit shall be
obtained at 745 W Colfax for the generator.
Temporary Certificate of Occupancy. No temporary emergency residential shelter permitted under this policy shall
be used or occupied until a Temporary Certificate of Occupancy (TCO) is issued by the Building Official indicating the
specific location and approved period of occupancy for which the certificate is issued. An unauthorized change to any
of those details voids the TCO.