Step 8. Review session will be conducted via Webex and may result in a list of corrections, which will
be emailed to the applicant 2 business days prior to the technical review session for correction and
addressed during review session.
Step 10. If the technical issues discussed during the review session are resolved at the time of the
review session or within the 24 hour window following the meeting, approvals will be documented
and permits will be issued. Alternately, if a resolution cannot be reached, the project will go through
a subsequent review session for a fee (refer to page 6 & 7).
Step 11. Following approval, project will go to Quality Assurance (QA) & Quality Check (QC),
simultaneously the ATR will verify other agency approvals. Projects not approved by other agencies
will be placed on hold until approved.
Step 12. Applicant will receive the final permit invoice and issued permit upon payment and alerted
via email.
Step 13. After permit issuance and posting of the job site, inspection will begin throughout the duration
of the project (Inspection Services for Businesses)
Accelerate Plan Review Guide VI 4/2021