CIP FY 24-28 9-7-23 FINAL Version - Flipbook - Page 259
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Wastewater
(1) PROJECT NAME: SEWER / EASTERN PLANT TURBINE UPGRADE
PROJECT STATUS: Existing in Edmunds
ACCT1#:
042-8600-535-66-95
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Upgrades to the Eastern Reuse System to service residential areas such as Heathrow,
Redtail, and Sorrento Springs. Currently, one service pump is not capable of maintaining
service at peak demand. The project will allow for a third pump to be available to service
residents in the event that one fails or requires maintenance.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
x
Expand infrastructure
Sewer Capital Projects - 8600
PROGRAM:
We are requesting additional funds $35,000 for engineering and
construction due to inflation.
x
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
22/23
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY 27/28
TOTAL
-
35,000
-
120,000
-
-
-
-
35,000
120,000
-
-
Timetable
35,000
120,000
155,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c.
x service level mainten.
maintains City desired level of service
2 - 5 Years out
d. x service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY27/28
2029-2033
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
33840 Cardinal Lane, Sorrento FL
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works
259
-