CIP FY 24-28 9-7-23 FINAL Version - Flipbook - Page 232
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Wastewater
(1) PROJECT NAME: SEWER / FLOATING SOLAR PANEL
PROJECT STATUS: NEW Project This Year
Sewer Capital Projects - 8600
PROGRAM:
ACCT1#:
042-8600-535-66-10
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Installation of floating solar panels on the west reclaim pond at the Eastern Wastewater
Plant. The project will connect to the electrical systems for the Eastern Wastewater Plant,
Eastern Water Plant, and the Sprayfield Pumping Station. Some funding may be achieved
through the Inflation Reduction Act of 2022. The payback period is currently calculated at
9.7 years.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
The project moved from 27/28 to 23/24; fund balance financing.
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
X
(4) ESTIMATED COST BY YEAR:
Current Year
22/23
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY 27/28
-
1,500,000
-
-
-
-
1,500,000
-
-
-
TOTAL
1,500,000
1,500,000
Timetable
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. X service level mainten.
maintains City desired level of service
2 - 5 Years out
d.
service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY27/28
2029-2033
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Eastern Reclaim Pond
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works
232