CIP FY 24-28 9-7-23 FINAL Version - Flipbook - Page 219
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water
(1) PROJECT NAME: WATER IMPACT / EASTERN WATER MAIN EXTENSION
PROJECT STATUS: NEW Project This Year
Water Impact Projects - 8600
PROGRAM:
ACCT1#:
065-8600-533-67-02
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
This project will be for the construction of 600 ft of 16” water main & cover the cost difference for upsizing the water main to the Cardinal Ln project. Approximately 2,000 feet of
water main will be upsized to 16 inch.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
X
Expand infrastructure
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
22/23
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY 27/28
-
300,000
-
-
-
-
300,000
-
-
-
TOTAL
300,000
300,000
Timetable
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
X
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c.
service level mainten.
maintains City desired level of service
2 - 5 Years out
d.
service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY27/28
2029-2033
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Eastern Plant
1) Water Impact Fee Fund 065
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works
219