CIP FY 24-28 9-7-23 FINAL Version - Flipbook - Page 218
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water
PROGRAM: Water Impact Projects - 8600
(1) PROJECT NAME: WATER IMPACT / RECLAIMED WATER MAIN EXPANSION HICKS DITCH RD
PROJECT STATUS: Existing in Edmunds
ACCT1#:
065-8600-533-67-37
ACCT2#:
ACCT3#:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
This project is the installation of approx. 1000’ of 12” PVC reclaim water main. The extension will supply reclaim water to portions of the North East section of the City. The construction will be by directional bore and open trench from Hicks Ditch Rd. East 1000’.
Project to expand reclaimed infrastructure. Added a project into 27/28
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
X
Expand infrastructure
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
22/23
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY 27/28
TOTAL
-
-
-
100,000
-
150,000
-
-
-
100,000
-
150,000
Timetable
250,000
250,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. X service level mainten.
maintains City desired level of service
2 - 5 Years out
d.
service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
FY27/28
2029-2033
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
CR 44/Hicks Ditch Rd.
1) Water Impact Fee Fund 065
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works
218
-