CIP Book FY 2023-27 - Final - Flipbook - Page 223
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Wastewater - 535
(1) PROJECT NAME: SEWER / LIFT STATION SUBMERSIBLE PUMPS
PROJECT STATUS: Existing in Edmunds
PROGRAM:
ACCT1#:
042-8600-535-66-43
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
This is an ongoing program to update and replace declining infrastructure components.
This is a permanent program to maintain the numerous lift station pumps.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
3510 - Collection and Lift Station
Added 26/27
x
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
TOTAL
a. Land Acquisition
b. Planning
c. Design
d. Architecture/Engineering
e. Site Development/Construction
f. Equipment,Vehicles, Etc
105,000 105,000 65,000 65,000 65,000 65,000 365,000
g. Contingency
h. Other
i. Project Additions/Changes
TOTAL
105,000 105,000 65,000 65,000 65,000 65,000 365,000
(5) PRIORITY:
Timetable
x
safety concern, hazardous condition, agency compliance, non-funca.
risk
tional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c.
x service level mainten.
maintains City desired level of service
2 - 5 Years out
d. service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
Current Year
YEARS
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY26/27
2028-2032
TOTAL
Change in Fuel Costs
- - - - - - - Change in Utility Costs
- - - - - - - Change in Maintenance
- - - - - Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Various
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Greg Dobbins - Director of Utilities
221