12.2 Construction Requirements Checklist
Confirm that all of the Construction Requirements have been included in construction
documentation for the proposed public building. Provide justification for any departure.
No
CONSTRUCTION REQUIREMENTS
1
INSPECTION POINTS
Confirm the construction principle of 'Inspection Points' as outlined in this document are
incorporated in construction documentation.
CONFIRM
2
TR ADE NAMES
Confirm the construction principle of 'Trade Names' as outlined in this document are
incorporated in construction documentation.
CONFIRM
3
YES | NO
HANDOVER
Confirm the construction principle of 'Handover' as outlined in this document are
incorporated in construction documentation.
CONFIRM
7
YES | NO
WARR ANTIES
Confirm the construction principle of 'Warranties' as outlined in this document are
incorporated in construction documentation.
CONFIRM
6
YES | NO
OPER ATION + MAINTENANCE MANUALS
Confirm the construction principle of 'Operation + Maintenance Manuals' as outlined in this
document are incorporated in construction documentation.
CONFIRM
5
YES | NO
AS CONSTRUCTED DR AWINGS
Confirm the construction principle of 'As Constructed Drawings' as outlined in this document
are incorporated in construction documentation.
CONFIRM
4
YES | NO
YES | NO
CONSULTATION
Confirm the construction principle of 'Involvement' as outlined in this document is
incorporated in construction documentation.
CONFIRM
CAMDEN PUBLIC BUILDING DESIGN MANUAL