BACKFILL WITH 90% SITE TOPSOIL 10% DOUBLE
WASHED RIVER SAND. SITE SOIL TO BE ASSESSED BY
COUNCIL REPRESENTATIVE. IF UNSUITABLE BACKFILL
WITH SOIL MIX AS PER RECOMMENDATION FROM
COUNCIL REPRESENTATIVE
BACKFILL WITH 90% SITE TOPSOIL 10% DOUBLE
WASHED RIVER SAND. SITE SOIL TO BE ASSESSED BY
COUNCIL REPRESENTATIVE. IF UNSUITABLE BACKFILL
WITH SOIL MIX AS PER RECOMMENDATION FROM
COUNCIL REPRESENTATIVE
REFER TO PLANTING SCHEDULE
FOR PLANT SIZE AND SPECIES
75 MIN.
REFER TO PLANTING SCHEDULE FOR
PLANT SIZE AND SPECIES
MIN.75mm DEPTH 'HORTBARK' MULCH 15MM SIZE AS
SPECIFIED OR APPROVED EQUIVALENT. DO NOT
MULCH UP AGAINST STEM OF PLANT
275
200
MIN.75mm DEPTH 'HORTBARK' MULCH 15MM SIZE
AS SPECIFIED OR APPROVED EQUIVALENT. DO
NOT MULCH UP AGAINST STEM OF PLANT
CULTIVATED SUB GRADE TO
MINIMUM DEPTH OF 150mm
CULTIVATED SUB GRADE TO
MINIMUM DEPTH OF 150mm
EXISTING SUB GRADE
EXISTING SUB GRADE
VARIES
GC VIROTUBE PLANTING WITH BA
GC GROUNDCOVER PLANTING
1.1
SECTION - TYPICAL
1.2
1:10 @ A1
SECTION - TYPICAL
335
175
175
335
335
335
335
335
GARDEN BED EDGE AS SPECIFIED
165
LOMANDRA LONGIFOLIA OR
GROUNDCOVER AS SPECIFIED
330
VARIES
VARIES
665
330 - VARIES PER PLANT SPECIES
665 - VARIES PER PLANT SPECIES
GC GROUNDCOVER PLANTING SETOUT
1.4
SECTION - TYPICAL
1:20 @ A1
REVISION DATE
DESCRIPTION
DRAWN
VERIFIED
APPROVED
A
DRAFT FOR REVIEW
NB
TV
XX
27/10/2022
APPROVALS
PROJECT
CAMDEN STANDARD DETAILS
TEAM LEADER
RECOMMENDED DATE: 27/10/2022
CAMDEN LGA
SHEET TITLE
GROUNDCOVER PLANTING