23 426870 Camden Standard Landscape Details - August 2023 - Flipbook - Page 72
DRAINAGE FLUSH POINT
OUTSIDE OF FALL ZONE
WET POUR RUBBER SOFTFALL
MULCH SOFTFALL PLAY
AREA. DEPTH VARIES
MIN. 150
275mm ROUND VALVE BOX WITH BLACK LID
PLACED INTO COMPACTED CRUSH ROCK.
FINISH FLUSH WITH WET POUR RUBBER
PVC NON SLOTTED PIPE RISER WITH
SCREW CAP TOP. WHERE POSSIBLE,
ALIGN ADJACENT TO HARD EDGE. ALLOW
MIN. 150mm SOFTFALL MULCH COVER
SUBSOIL DRAINAGE
200
SLOTTED DRAINAGE LINE IN FILTER SOCK
TO BOTTOM OF DRAINAGE TRENCH. FALL
CONTINUOUS TO JUNCTION PIT OR
DRAINAGE OUTLET
PVC NON SLOTTED PIPE RISER WITH
SCREW CAP TOP. WHERE POSSIBLE,
ALIGN ADJACENT TO HARD EDGE
EXISTING SUB GRADE
200
300
FP DRAINAGE FLUSH POINT IN PLAYGROUND
FR DRAINAGE FLUSH POINT IN WE
1.1
1.1
SECTION - TYPICAL
1:10 @ A1
SECTION - TYPICAL
PROPOSED PLANTS AS SPECIFIED. REFER PLANT
SCHEDULE AND LANDSCAPE PLANS
+
+
100 Ø SOLID WALL PIPE RISER FLUSH POINT.
AT COMMENCEMENT OF RUN AND JUNCTIONS.
MAX SPACING 60m
+
+
+
+
+
+
+
+
+
+
+
SLOTTED PVC PIPE TO BASE OF PIT
STORMWATER OUTLET PIPE
VARIES. REFER PLAN (2500 MIN)
+
100 Ø SOLID WALL PIPE RISER FLUSH POINT.
TOP OF RODDING POINT TO FINISH 100mm ABOVE
G.L. FIT WITH SEALED SCREW CAP
+
+
+
PROPOSED PITS AS SPECIFIED.
SIZE, LOCATION, AND LEVELS
AS SHOWN ON PLANS
VARIES. REFER PLAN
FG DRAINAGE FLUSH POINT ARRANGEMENT PLAN IN GARDEN BED
1.2
SECTION - TYPICAL
1:10 @ A1
REVISION DATE
DESCRIPTION
DRAWN
VERIFIED
APPROVED
A
DRAFT FOR REVIEW
NB
TV
XX
27/10/2022
APPROVALS
PROJECT
CAMDEN STANDARD DETAILS
TEAM LEADER
RECOMMENDED DATE: 27/10/2022
CAMDEN LGA
SHEET TITLE
FLUSH POINTS
1:1