DEFINE what is meant by a hold point and who is responsible for identifying the
requirement for them.
Hint:
Tutor Reference:
6
Procedural Guide Paragraph 5.3.6 or BS 5975 Clause 3.29
LO 9.3 (TWS), 10.3 (TWC), CITB 3B, 5, 6
DESCRIBE inspection and test plans (ITP) and who is responsible or preparing it.
Hint:
Tutor Reference:
Procedural Guide Paragraph 5.4.5 or BS 5975 Clause 3.30