TWSTC Study Pack - Book - Page 36
Table 1 and Table 2
Using BS5975 'Table 1' and 'Table 2', IDENTIFY the design check category, implementation
risk classification and who would be authorised to issue permits relating to structures both
ABOVE and BELOW the ground.
4
5
Open steel-mesh fencing,
temporary measure until
timber hoarding design has
been approved, installed on a
Monday morning by
inexperienced site labourers
new to site
Temporary stairway and
landing edge protection
handrail, fixed using
conventional methods,
installed by senior operatives
from contractor responsible
for installing precast stairs
Access trackway used to
protect the temporary road
surface and provide traction
for construction plant,
installed by a well-established
civil engineering contractor
10. Referring to table 2,
what is the design
check category?
13. Referring to table 2,
what is the design
check category?
16. Referring to table 2,
what is the design
check category?
A.
B.
C.
D.
Category
Category
Category
Category
0
1
2
3
11. Referring to table 1,
what is the
implementation risk
classification?
A.
B.
C.
D.
Very Low
Low
Medium
High
12. Referring to table 1,
who can issue the
permit to bring into
use?
A.
B.
C.
D.
36
6
TWS
SC TWC
PC TWC
All the above
A.
B.
C.
D.
Category
Category
Category
Category
0
1
2
3
14. Referring to table 1,
what is the
implementation risk
classification?
A.
B.
C.
D.
Very Low
Low
Medium
High
15. Referring to table 1,
who can issue the
permit to bring into
use?
A.
B.
C.
D.
TWS
SC TWC
PC TWC
All the above
A.
B.
C.
D.
Category
Category
Category
Category
0
1
2
3
17. Referring to table 1,
what is the
implementation risk
classification?
A.
B.
C.
D.
Very Low
Low
Medium
High
18. Referring to table 1,
who can issue the
permit to bring into
use?
A.
B.
C.
D.
TWS
SC TWC
PC TWC
All the above