TWSTC Study Pack - Book - Page 30
Execution risk controls
Acting as either the designated individual, the temporary works coordinator or the temporary
works supervisor, outline the general control measures that should be taken in relation to
the workmanship, materials, experience, and manner of use for the trench lining system/
scaffolding. These are EXECUTION RISKS.
IDENTIFY five examples of how experience could be controlled.
3
Top tip: think worst case, i.e., inexperienced and/or unsupervised workforce who are
unfamiliar with process and/or equipment.
Structure type:
IDENTIFY five examples of how manner of use could be controlled.
4
Top tip: think worst case, i.e., equipment being overloaded beyond its limitations, or
misused in use.
Structure type:
30
© 2B Trained Ltd | Temporary Works Training Course l Study Pack l Exercise 4 l Document Version: 4.00