TWSTC Study Pack - Book - Page 22
The design brief
Scenario 1
You are a site agent working for a civil engineering contractor and you have been tasked with
installing drainage for a new 4-storey office block.
The redundant factory has been demolished and the ground contamination and the Japanese
knotweed have been removed. The foundation for the new 4-storey office block has been
recently completed.
Your task, using the site plan, is to complete the design brief for a trench lining system to
support the vertical sides of the excavation to enable you to install the drainage.
2
LIST the information the temporary works designer should provide to you and the
considerations and KEY FEATURES the proposed designed solution should include.
These are also expressed as DESIGN CONTROLS or OUTPUTS.
22
© 2B Trained Ltd | Temporary Works Training Course l Study Pack l Exercise 3 l Document Version: 4.00