What is the main reason for preparing a design brief?
A
It will allow the same temporary works equipment to be used in all
locations
B
It must be used to inform the client what temporary works are being
constructed
C
It is prepared to serve as the basis for subsequent design decisions,
calculations, drawings and design checks
D
It satisfies insurance policies
2
If there is more than one contractor, a Principal Contractor
Your
Correct
must be appointed by the client. What must therefore be
answer answer
written to manage the interfaces between contractors?
A
Critical Path Plan
B
Construction Phase Plan
C
Control Path Plan
D
Cost Projection Plan
3
Your
Correct
It is the TWC's responsibility to maintain a Temporary Works
answer answer
Register (TWR). Why should a TWR be maintained?
A
It lets you know who is one site at any one time
B
It tell you what vehicles are on site
C
It allows the client to plan and continuously monitor temporary works
D
It ensures temporary works have been identified and that they are
being continuously monitored