7
EXPLAIN what responsibility the Supplier has in relation to the safe execution of
temporary works
Hint:
Tutor Reference:
8
BS 5975 Clause 10.3
LO 5.1, CITB 3B, 6
IDENTIFY the key stages that should be addressed in a temporary works process by
moving the following seven key stages into the correct sequence.
Stage
Planning
1.
Implementing the removal
2.
Checking design
3.
Identifying
4.
Implementing the build
5.
Designing
6.
Monitoring use
7.
Hint:
Tutor Reference:
60
What is the correct sequence?
Procedural Guide Paragraph 3.3.8
LO 4.1, CITB 5