The design brief
Scenario 2
You are a project manager and the appointed principal contractor temporary works coordinator.
The redundant factory has been demolished and the ground contamination and the Japanese
knotweed have been removed. Drainage works around the boundary of the new 4-storey office
block have recently been completed.
A scaffolding contractor has been appointed and your task, using the site plan below, is to
complete the design brief for a general-purpose access scaffolding to assist building a new 4storey office block.
1
LIST the information you should provide to the temporary works designer so they can
provide you with a suitable solution.
These are also expressed as DESIGN CONSIDERATIONS or INPUTS.