The design brief
Scenario 1
You are a site agent working for a civil engineering contractor and you have been tasked with
installing drainage for a new 4-storey office block.
The redundant factory has been demolished and the ground contamination and the Japanese
knotweed have been removed. The foundation for the new 4-storey office block has been
recently completed.
Your task, using the site plan, is to complete the design brief for a trench lining system to
support the vertical sides of the excavation to enable you to install the drainage.
1
LIST the information you should provide to the temporary works designer so they can
provide you with a suitable solution.
These are also expressed as DESIGN CONSIDERATIONS or INPUTS.