5.3 BRINGING TEMPORARY WORKS INTO USE
5.3.1
Bringing a structure into use in the ‘implementation phase’ involves a few key steps
as follows:
Step
Who is likely to be involved
a. Reviewing risk
assessments and method
statements prior to
commencement
Project Lead/Safety Manager/Designated Individual/TWC
b. Briefing the installation
team
Designer/Project Lead/Safety Manager/Designated
Individual/TWC/TWS/Lead installer/supervisor/foreman
and/or TWC/TWS/supervisor/foreman/installation team
c. Inspecting prior to
installation
d. Inspecting during
installation
e. Inspecting prior to use
f. Issuing a permit to
use/load
5.3.2
Lead installer/supervisor/foreman and/or
TWC/TWS/supervisor/foreman and/or TWC/TWS or another
competent person
Note: a permit to proceed may be required during
construction as defined in the inspection and test plan
(ITP)
An authorised TWS/ an authorised SC TWC or the PC’s TWC
The review of risk assessments and method statements should be undertaken well in
advance of the ‘implementation phase’ and may be initiated in the ‘planning phase’
or as concurrent activity in the ‘design phase’.
figure 1 – CITB form template - example of a method statement review (extract)
Version 2 © mytemporaryworks 2023 | The control of temporary works – procedural guide