5.2 TEMPORARY WORKS IMPLEMENTATION PLAN
5.2.3 The TWIP links directly to the arrangements that are in place as detailed in the
construction phase plan (CPP). The table below shows the considerations when planning
‘construction works’ that influences ‘temporary works’ that should be considered within the
TWIP.
Heading
1. Description of the
project
2. Management of the
work
3. Arrangements for
controlling significant
site risk - this relates
to CDM Part 4
general
requirements for all
construction sites
4. The health and safety
file
5. Significant design and
construction hazards
5.2.4
Arrangements that could be included in the CPP that
should be considered in the TWIP
Project description
Programme details
Key Dates
Details of the project team
Extent and location of existing records
Information on existing structures
Structure and responsibilities (including PC DI, PC TWC)
Arrangements for monitoring and review
Site rules and expectations
Arrangements for compliance with part 4 of the CDM
regulations such as:
o Selecting and controlling sub-contractors (PAS 91 - PQQ)
o Handling design changes
o Exchanging information between client, designers, PD and
contractors
o Cooperation between the project team and subcontractors
o Producing and approving RAMS
Delivery, removal and use of equipment taking into account
of any risks to the public or environment
Accommodating adjacent land use
Preventing falls
Work involving the assembly and/or dismantling of
prefabricated components/equipment
Stability of structures (CDM Regulation 19)
Working on/in excavations (CDM Regulation 22)
Residual risks to be considered when using, maintaining,
renovating or demolishing
Design assumptions and suggested work methods,
sequences, and controls
Arrangements for co-ordination of on-going design works
and design changes
Significant risks identified during design
Materials/equipment required requiring particular precautions
There is no specific format for the TWIP however it should follow the guidance provided
in BS5975 and company procedures. If produced by others the PC’s TWC or SC’s TWC
is responsible for reviewing the content.